|
![[ Dock Express 10 arrives with the 2 new cranes ]](../images/Trapac%20arriving.jpg)
Trapac container cranes
arriving at Oakland on the Dock Express 10
Project Summary
In June
1999, the Dock Express 10 delivered one each 4-th generation
container crane to the Trans Pacific Container Service Corporation
terminals in Oakland, CA and Los Angeles, CA, respectively. The cranes
were built by Mitsui Engineering & Shipbuilding Co., Ltd. in Japan and
Dockwise Shipping BV was contracted for the delivery. These cranes were
transported together, fully erect, with the boom of the aft Oakland
crane supported on the APEX of the forward Los Angeles crane.
Argonautics Marine Engineering was hired to supervise the offloading
operations. The Oakland crane was offloaded, using the so-called
"Miami" method offloading. After removal of the boom supports and tie
downs, the 1,000 t crane was skidded aft over the ship's outriggers
until the crane's landside sill beam could be lowered onto a set of
jack boogies, which moved the crane further over the quay. Once in
position, the waterside sill beam was temporarily supported on wood
blocks. The landside was then jacked up for installation of the landside trucks. The ship was then moved forward, the waterside was
picked up so that the waterside trucks could be rotated after which the
waterside trucks were lowered onto the rails. After reloading of the
offloading equipment, the Dock Express 10 sailed to Los Angeles
for delivery of the second crane.
Because of
the height restriction of the Vincent Thomas bridge, the crane was
stowed inside the cargo hold as low as possible. The bridge passage
even required this hold to be partly filled with ballast water to
increase the vessel's draft as much as possible. The 1,000 t crane was
offloaded by skidding it aft over the outriggers and landing it on wood
blocks on the quay. In two steps, the crane was lifted higher after
which the trucks could be installed.
Scope
of Work
The project scope
included:
-
Coordination of activities during offloading;
-
Liaison with ship crew, client and its subcontractor,
Bickerton Ironworks;
-
In
Oakland: setting-up of rail track and jack boogies as per the
Dockwise Offloading Procedure;
-
In Los
Angeles: setting-up of wood blocks as per the Dockwise Offloading
Procedure;
-
Provision of on-site supervision during actual discharge operations.
Project Photographs
|
|
|
Once all preparations were completed, the Dock Express 10 is maneuvering into a stern to position to offload the Oakland crane. |
|
|
|
The landside sill beam of the Oakland crane is set down on the self-propelled jack boogies. |
|
|
|
The sheaves on top of the APEX cleared the Vincent Thomas bridge with about 2 feet clearance. |
|
|
|
The Los Angeles crane is temporary landed onto wood blocks before raising it for installation of the trucks. |
|
|
|