![[ Arrival of the cranes loaded on the Weeks 297 ]](../images/Eddystone%20Cranes.JPG)
Arrival of the two STAR cranes loaded on the barge Weeks 297
Project Summary
For the relocation of two older
STAR cranes from Jersey City, NJ, to Eddystone, PA, in December 2005, Argonautics
Marine Engineering was hired to provide the loading and offloading ballast
calculations, barge design motions, and the marine warranty survey for the tow. The
2
cranes, each weighing approximately 680 t, were loaded onto the 250 x 75 ft cargo barge Weeks
297
with multi-wheel trailers
and secured with pipe bracings. Because of the short tow distance with
limited exposure (about 200 nmiles total, of which 125 nmiles in open
water), the crane seafastenings were designed for a good weather voyage
only with a conditional departure subject to a favorable weather
forecast. Because of the total height of the cranes on the barge, the
Delaware Memorial Bridge could only be passed at low water.
Upon receipt of the tow approval
certificate and a good weather forecast, the 4,300 hp tug Michaela
McAllister hooked up and and the tow departed Jersey City. Less than 48
hours later, the tow arrived
safely in Eddystone where the cranes were
offloaded.
Scope
of Work
The project scope
included:
-
Loading and offloading ballast
calculations;
-
Provide design criteria and resulting
barge motions/crane accelerations;
-
Review of the proposed
crane reinforcement
and seafastening plan;
-
Survey the cranes with respect to
tow readiness and internal securings;
-
Survey the
seafastening bracing installation;
-
Survey the seafastening of the
miscellaneous cargo items and all loading equipment;
-
Inspect the barge and its towing
connections.
Acknowledgement
Photograph courtesy
of Penn Terminals Inc.
Project Photographs
|
|
|
Outside bracing pipes on land side. |
|
|
|
Inside bracings. |
|
|
|
Securing of festoon cable. |
|
|
|
Lashing of the load-out trailers. |
|
|
|