![[ Crane boom lifted free from support ]](../images/Samsung%20crane.jpg)
Crane boom lifted free from temporary support
Project Summary
In 1997, a
Samsung container crane was relocated from the old to the new Hanjin
terminal in Long Beach by Bickerton Iron Works. For this relocation, a
Crowley 400 x 100 x 20 ft flat top cargo barge was used. The 900 t crane
was lifted off its rails by a large number of hydraulic dollies, which
also provided the means to roll the crane onto the barge. Steel bridge
pieces spanned the gap between the barge stern and the quay. On November
6, 1997, with incoming tide, the crane was rolled onto the barge and
lowered on temporary blocks. The boom was then lowered onto a boom
support after which the A-frame could be removed. This was needed to
clear the power cables, spanning the access canal to the new terminal.
Less than a week later, the crane was safely rolled off the barge and
lowered onto its rails at the new Hanjin terminal .
Scope
of Work
The project scope
included:
-
Modeling of the barge hull for the ballast analysis;
-
Simulation of the crane roll-on and roll-off operations and optimize
ballast procedure;
-
Provision of on-site assistance during actual operations and
controlling of the barge ballast operations.
Project Photographs
|
|
|
Setting up the first row of waterside dollies. |
|
|
|
First row of dollies coming off the ramp plates. |
|
|
|
Getting ready to pull the crane of the barge. |
|
|
|
Waterside dollies at the barge stern, getting ready to roll off. |
|
|
|