![[ Barge with bridge capzised ]](../images/Rancocas%20Bridge%20Accident.jpg)
Barge with bridge capsized at the construction site
Project Summary
In April 2001, the cargo barge Coen
260, carrying the Rancocas Creek steel arch bridge, suddenly capsized and
came to rest at a 46 deg angle, with the bridge resting on a mobile
crane and the pier. The bridge was being assembled and just days away
from installation. Argonautics Marine engineering became involved in the
bid stage and assisted Rigging International with securing the recovery
and installation contract. Once the contract was obtained, the accident
was investigated and a root cause report produced. A detailed uprighting
procedure was developed, including maximum required pulling and
restraining forces at various critical stages of the operation.
Once all
righting equipment was in place, on-site assistance was provided during
the actual operation, which was successfully executed on July 27, 2001.
Additional stability was provided with 4 small sectional barges,
temporarily mounted to the sides of the Coen 260 barge.
Four days after uprighting, the bridge was floated in position over the
piers. By ballasting the barge down, the bridge was lowered onto its
bearings.
Scope
of Work
The project scope
included:
-
Investigation
of the accident, resulting in a root cause report;
-
Design of the righting procedures
and establish maximum required forces at each critical step;
-
Check of stability throughout the
righting and design of mounting hardware for temporary stability
sponsons;
-
Design of ballast procedures for
final installation of the bridge onto its piers;
-
Provision of on-site assistance
during actual uprighting an installation operations.
Project
Articles
This uprighting operation was closely
followed by the local media. Newspaper articles appeared in the
Burlington County Courier...
and in the Courier Post...![[ Uprighting articles in Courier Post ~ .4 MB ]](../images/PDF.gif)
Project
Photographs
|
|
|
Sectional barges were mounted to the capsized barge to ensure its stability after uprighting. |
|
|
|
Deballasting the capsized barge signaled the start of the righting operation. |
|
|
|
Barge partly uprighted and free floating again as dawn sets in. |
|
|
|
Barge uprighted and stable. Bridge was successfully installed four days later. |
|
|
|