Project Summary
In October 2000, the
semi-submersible drilling rig Ocean Baroness was dry transported
from the US Gulf to Singapore by the heavy-lift ship Mighty Servant 1.
Because this was the first time a rig of this type (4 tubular floaters,
12 columns) was transported, a structural analysis of the rig was
reviewed. An existing detailed StruCAD*3D model of the rig was modified
and used to study the behavior of the structure when subjected to the
design dynamic loadings of the transport. The FEM analysis showed that
most beam and plate stresses were within the allowable limits, but beam
seas headings should be avoided.
Scope
of Work
The project scope
included:
-
Check
environmental criteria and provide independent motion response data;
-
Review
available structural analysis of the rig;
-
Define
sea state limitations, as function of wave period and heading.
Acknowledgement
Photograph courtesy
of Matthews-Daniel Company.
|