![[ The Molikpaq rig successfully mated to the spacer ]](../images/Molikpaq.jpg)
The Molikpaq rig successfully mated to the spacer
structure
Project Summary
In March
through May of 1998, Argonautics Marine Engineering was part of a
multi-national team of specialists, involved in the mating operation of
the Molikpaq rig onto a purpose built spacer structure in Okpo,
Korea.
The
Molikpaq, a bottom founded, mobile arctic caisson type rig, has been
refurbished by Daewoo Heavy Industries, Ltd. in Okpo, Korea for
installation offshore Sakhalin. Since this new location is in deeper
waters, a 16 m high steel structure was designed and built to increase
the rig's hull depth. This "spacer" was built in sections at the Amur
Shipbuilding Plant and assembled in Bolshoi Kamen. The octagonal, donut
shaped 15,000 t spacer measured 110 x 110 m and was outfitted with 3
stability towers. A hydraulic operated valve system was installed for
gravity ballasting. The Ballast Control Container was mounted on the
center buoyancy tower. Upon completion in Russia, the spacer was towed
to the Daewoo Heavy Industries, Ltd. shipyard for final preparations and
testing before the mating operation. Computer simulations were used to
optimize the spacer submersion procedure.
On May 23,
the spacer was towed out to the carefully selected mating site and
moored to a spread of pre-installed anchors and winch barges. A work
barge, outfitted with generators and compressors (providing the
compressed air needed for deballasting) was hooked up to the center
tower. Following the procedure, the spacer was slowly submerged by free flooding the main ballast
tanks while maintaining trim and heel control with the corner tanks.
On May 26,
the Molikpaq was towed to the mating site and connected to the
anchored winch barges. While monitoring the position relative to the
submersed spacer with underwater cameras, the Molikpaq was slowly
winched into position against 3 stoppers. Once in position, the spacer
was deballasted, lifting the 43,000 t Molikpaq out of the water.
Final position of the Molikpaq was confirmed to be within 5 mm,
well within the 50 mm tolerance. The successfully mated units were unmoored and towed
back to the yard for welding of the Molikpaq bottom to the spacer
pedestal tops and completion of the refurbishing. In August of 1998,
the rig was towed to Sakhalin and successfully set down.
Scope
of Work
The project scope
included:
-
Attending and working as a member of the Mating Task Force Team;
-
Reviewing of all engineering output and procedures;
-
Reducing the planned
offshore time from 14 days to 5 days;
-
Providing experience and operational input for the procedures;
-
Design
of safe and workable ballast procedures for the spacer
submersion;
-
On-site training of the Daewoo ballast team;
-
Supervision of the actual spacer ballast and Molikpaq mating
operations.
Project Paper
A project paper presented at the Northern California Section meeting
of the SNAME, Berkeley, CA, on June 10, 1999, can be downloaded in PDF
format.
Mating
of the Molikpaq Drilling Rig...
Project Video
A short video shows the mating operation and
welding of the drilling unit to the spacer structure, all filmed by
Daewoo. Requires Windows Media Player.
Molikpaq Mating
Operation...
Project Photographs
|
|
|
The spacer structure arrived at the Daewoo yard after a long tow from Russia. The ballast system was tested and some modifications were made. |
|
|
|
Slowly the spacer deck submerses as its tanks are flooded, in accordance with the ballast procedure. Positive stability was maintained at all times. |
|
|
|
Using local tugboats, the Molikpaq is maneuvered over the submersed spacer. Final positioning was done using winches mounted on anchored barges. |
|
|
|
After achieving firm contact and confirmation of correct positioning, the combined unit was deballasted with a small trim and list. |
|
|
|