![[ Modules loaded in hold of Ocean Atlas ]](../images/Ocean%20Atlas%20with%20Convection%20Modules.JPG)
Convection modules loaded on a false deck inside the M/V
Ocean Atlas
Project Summary
In April 2007, a
total of 24 large convection modules were to be loaded onto the heavy-lift
project ship Ocean Atlas. These modules weighed between 60 and
120 t and because direct stacking was not allowed, false support decks
were to be installed in the vessel's holds. Argonautics Marine
Engineering was hired to design these false decks and their supports and
to design the lashing of the convection modules - all with very short
notice. The false decks were limited to sets of steel cross beams in way
of the module support points only, resting on 8 ft high stacks of crane
mats and timbers. The final construction drawings were delivered on time
to ensure the installation of the decks and loading of the modules could
take place without any delays. In Houston, TX, the convection modules
were loaded on the false decks and successfully delivered to the port of Ras Laffan after an uneventful voyage.
Scope
of Work
The project scope
included:
-
Design the false decks and their
supports, using available materials;
-
Provide detailed construction
drawings;
-
Design the lashing of
the modules, using clips and lashing chains.
Acknowledgement
Photograph courtesy
of Intermarine LLC
|