![[ Pedstrian bridge is rotated in place ]](../images/San%20Joaquin%20Foot%20Bridge%20Installation.jpg)
Pedestrian bridge is picked up from barge and rotated
in place
Project Summary
Using a Manitowoc 888 Series 2
crawler crane on a 210 x 54 x 13.5 ft cargo barge, a new pedestrian
bridge was installed over the San Joaquin River in September 2004. The
crawler crane was first rolled onto the barge, after which it picked the
bridge in 3 separate sections from the shore for assembly into a single
200 ft long piece on the side of the barge. After assembly, the barge
with crane and bridge was maneuvered into place. The complete 100 t
bridge section was then lifted up and rotated until is was over its end
supports and installed. During the crane rotation, the barge was
ballasted to limit its list.
Scope
of Work
The project scope
included:
-
Check suitability
cargo barge;
-
Stability and ballast
calculations for the various phases of the operation;
-
Check hull bending stresses for
the various phases of the operation;
-
Review deck
strength analysis.
Acknowledgement
Photograph courtesy
of Rigging International.
|