|
![[ Dock Express 10 arrives with 2 cranes ]](../images/Hyundai%20Offloading%20Arrival.jpg)
Dock Express 10 loaded
with 2 cranes arrives in Charleston
Project Summary
In August
2000, the Dock Express 10 delivered two 4-th generation container
cranes to the Wondo Container Terminal in Charleston, South Carolina. To
clear the Cooper River bridge, the vessel was ballasted down to maximum
draft.
Argonautics Marine Engineering was hired to supervise the so-called
"Miami" method offloading. After removal of the tie downs, the 1,100 t
cranes were skidded aft over the ship's outriggers until the crane's
landside sill beam could be lowered onto a set of jack boogies, which
moved the crane further over the quay. Once in position, the waterside
sill beam was temporarily supported by wood blocks, enabling the ship to
move forward. The waterside was then picked up again and the waterside
trucks could be rotated and lowered onto the rails. The landside was
then jacked up for installation of the landside trucks after which these
were also lowered onto the rails. After 3 days preparations, both cranes
were offloaded in 3 consecutive days, within the favorable tide windows.
Scope
of Work
The project scope
included:
-
Coordination of activities during offloading;
-
Liaison with ship crew, client and its subcontractor;
-
Setting-up of rail track and jacking boogies as per the Dockwise
Offloading Procedure;
-
Provision of on-site supervision during offloading operation.
Project Photographs
|
|
|
The boom of the forward crane clear the Cooper River bridge with an adequate margin. |
|
|
|
The first crane completely offloaded. Getting ready to install the crane trucks. |
|
|
|
The landside sill beam is jacked up to install the trucks. |
|
|
|
The second crane being rolled/skidded off the ship. |
|
|
|