In February 2006, a
Huisman 800 t heavy-lift mast crane was loaded onto the container vessel
Pangani for transport from Schiedam, the Netherlands, to
Shanghai, China. The grillage and lashing arrangements were designed based on standard Germanisher Lloyd's
requirements, which were compared to the IMO guidelines for lashing of
heavy cargoes on board container ships. The 635 t heavy mast crane was
successfully loaded using 2 floating shear leg cranes, secured, and
after an uneventful voyage safely delivered in Shanghai.
Scope
of Work
The project scope
included:
-
Verify the motion/acceleration
criteria for the transport;
-
Review proposed
grillage and lashing arrangements;
-
Provide guidelines for
the local surveyor.