![[ Hitachi crane on stern of barge ]](../images/Hitachi%20Crane.jpg)
Hitachi crane on stern of barge, ready for offloading
Project Summary
A 27 year old Hitachi container
crane needed to be relocated from one berth to another berth, both
within Los Angeles port limits. The 800 t heavy crane was lifted off its
rails using hydraulic dollies. Propulsion was provided by three large
trucks. A Crowley 400 x 100 x 20 ft cargo barge was chartered for the move.
Steel bridge pieces spanned the gap between the barge stern and the
quay.
On December 10, 1999, with incoming tide,
the crane was rolled onto the barge 419. The barge was then ballasted down
to ensure safe passage under the Vincent Thomas bridge at low tide later
that day. Next day, at the beginning of the outgoing tide, the crane was
safely rolled off the barge and lowered onto its rails at the new berth.
Scope
of Work
The project scope
included:
-
Modeling of the barge hull for the ballast analysis;
-
Simulation of the crane roll-on and roll-off operations and
optimization of ballast procedures;
-
Provision of on-site assistance during actual operations and
controlling of the barge ballast operations.
Project Photographs
|
|
|
Trucks push crane slowly onto barge. |
|
|
|
Bollard barely clears crane trucks. |
|
|
|
Last waterside dollies on barge. |
|
|
|
Barge towed to offloading quay. |
|
|
|