|
![[ Arrival of the Dock Express 10 in Long Beach ]](../images/Hanjin%20arrival%20Dock%20Express%2010.jpg)
Dock Express 10 arriving
at the Hanjin terminal in Long Beach
Project Summary
In July
1997, the Dock Express 10 delivered the last two of a series of six 4-th
generation container cranes to the new Hanjin terminal in Long Beach,
CA. The cranes were built by Mitsui Engineering & Shipbuilding Co., Ltd.
in Japan and Dockwise Shipping BV was contracted for the delivery. Because of
the Gerald Desmond bridge passage with its 155 ft height restriction,
these cranes were transported only partly erect, with their fully
assembled top sections temporarily secured low between the legs.
Argonautics Marine Engineering was hired
to supervise the so-called "Miami" method offloading. After removal of
the boom supports and tie downs, the 1,100 t cranes were skidded aft
over the ship's outriggers until the crane's landside sill beam could
be lowered onto a set of jack boogies, which moved the crane further
over the quay. Once in position, the waterside trucks could be rotated
and the waterside trucks were lowered onto the rails. The landside was
then jacked up for installation of the landside trucks after which
these were also lowered onto the rails.
Scope
of Work
The project scope
included:
-
Coordination of activities during offloading;
-
Liaison with ship crew, client and its subcontractor, Rigging
International;
-
Setting-up of rail track and jack boogies as per the Dockwise
Offloading Procedure;
-
Provision of on-site supervision during actual discharge operations.
Project Photographs
|
|
|
Vessel mooring stern to for offloading of the second crane. |
|
|
|
Landing the landside silbeam on the Dockwise self-propelled hydraulic jack boogies. |
|
|
|
Rotating the waterside crane trucks before lowering the waterside onto the rails. |
|
|
|
Second crane safely offloaded. Installing the landside crane trucks. |
|
|
|