Project Summary
Two luffing-type shipunloaders were
delivered to the Guacolda development in Huasco, Chile, in February
1995. These shipunloaders, designed and built by Sade Vigesa, had been
erected at the Verolme yard in Angra dos Reis, Brazil. For the ocean
transportation, the heavy-lift dockship Stakhanovets Yermolenko
was contracted. The shipunloaders, each weighing approximately 465 t,
were lifted onto the heavy-lift ship using the Verolme gantry crane and
were then secured for the voyage using steel brackets and pre-fabricated
pipe bracings. The ship rounded Cape Horn without any problems.
Upon arrival, the seafastenings were cut
and the shipunloaders were rolled off the ship, using a set of 11
hydraulic dollies and a shore-mounted pulling winch. The extreme height
of the quay, combined with the open ocean swell, posed a significant
challenge for the offloading. Once offloaded, the shipunloaders were
rolled to their foundations and set down with an accuracy of less than 2
mm.
Scope
of Work
The project scope
included:
-
Surveys of the loading and offloading locations;
-
Selection of optimal transport vessel;
-
Preparation of the loading procedures;
-
Preparation of the optimum stowage arrangement;
-
Establishment of design wave and wind criteria for the voyage around
Cape Horn;
-
Stability and ship motion analyses;
-
Full
structural analysis of the unloaders subjected to dynamic loading
during transport;
-
Structural analysis of the unloaders subjected to the dolly loads
during offloading;
-
Designs for internal strengthening, grillage and seafastenings;
-
Analysis of local strength of heavy-lift ship subjected to support
loads;
-
Preparation of offloading procedures and design of all related
equipment;
-
Calculations of ship's draft, trim and stability for offloading;
-
Structural analysis of the vessel's stern ramp subjected to high
dolly loads;
-
On-site supervision of loading, seafastening, and offloading
operations.
Project
Article
This successful transportation of the
Guacolda shipunloaders was featured in the May 1995 issue of the
"Maritime Reporter and Engineering News"...
Project Photographs
|
|
|
The shipunloaders were lifted onto the heavy-lift ship with the yard's large gantry crane. |
|
|
|
The shipunloaders were placed on loadspreaders and seafastened to the ship. |
|
|
|
The Stakhanovets Yermolenko moored stern to for offloading of the first unloader. |
|
|
|
The second shipunloader safely offloaded and in process of getting positioned over its foundation. |
|
|
|