|
![[ Project site ]](../images/GIIW%20Bypass%20-%20Installing%20the%20sheet%20piles.jpg)
The project site where
the gate will be built
Project Summary
For the GIIW Bypass Gate Tremie Coverage concrete pour, a
large number of truckloads of concrete were required. These loads were
delivered by driving the mixer trucks onto flat deck cargo barges, tow
the barges to the construction site, and dump the concrete into a
Maxcrete hopper on a pump barge for pumping into a placing boom. To make
the cement chutes work with the Maxcrete hopper, the pump barge was
ballasted down to a minimum freeboard. A total of 6 cargo barges of 150
x 54 ft were used, each shuttling 6 mixer trucks at the time. To load
the trucks onto the barge decks, 2 ramps were built, each consisting of
an aggregate upslope and an hinged existing steel Ro/Ro ramp.
Argonautics Marine Engineering attended a test run with 6 loaded mixer
trucks at the construction site in New Orleans on October 19, 2009. The
following weekend, over 500 concrete truck loads of cement were
delivered to the construction site.
Scope
of Work
The project scope
included:
-
Feasibility check of the cement truck barge concept;
-
Stability calculations for the loaded
truck barges;
-
Calculate the behavior of the barges
during the loading of the trucks;
-
Deck strength check for the various
truck barges;
-
Stability calculations for the cement
pump barge;
-
Design of the cement boom tower
foundations;
-
Ballast plan for the pump barge with minimum freeboard;
-
Stability calculations for a barge
loaded with 2 mobile cement pump trucks;
-
Verify the strength of the 2
available Ro/Ro ramps;
-
Design supports for one of the ramps;
-
Witness the truck driving/parking tests;
Project Photographs
|
|
|
The concrete pump barge with 2 elevated pump arms |
|
|
|
Testing the Ro/Ro ramp with a loaded cement truck |
|
|
|
Test parking the cement truck on the cargo barge |
|
|
|
Pouring concrete into the cement hopper on the pump barge |
|
|
|