|
![[ Dock Express 10 arrives with 3 cranes ]](../images/Freeport%20Arrival.jpg)
Dock Express 10 loaded
with 3 cranes arrives in Freeport
Project Summary
In
September 1999, the Dock Express 12 delivered three 4-th
generation container cranes to the Phase II extension of the Freeport
Container Terminal, Freeport, Bahamas. The cranes were built by Hyundai
Heavy Industries in Korea and Dockwise NV was contracted for the
delivery. Because of the Panama Canal passage with its 205 ft height
restriction for the Bridge of the
Americas, these cranes were
transported only partly erect, with their fully assembled top sections
temporarily secured low between the legs at different levels to allow
for efficient nesting of the cranes.
Argonautics Marine Engineering was hired to supervise the offloading.
After removal of the boom supports and tie downs, the 1,100 t cranes
were skidded aft over the ship's outriggers until the crane's landside
sill beam could be lowered onto a set of jack boogies, which moved the
crane further over the quay. Once in position, the waterside sill beam
was temporarily supported by wood blocks, enabling the ship to move
forward. The waterside was then picked up again and the waterside
trucks could be rotated and lowered onto the rails. The landside was
then jacked up for installation of the landside trucks after which
these were also lowered onto the rails. After 2 days preparations, these
three cranes were offloaded in 3 consecutive days.
Scope
of Work
The project scope
included:
-
Coordination of activities during offloading;
-
Liaison with ship crew, client and its subcontractor;
-
Setting-up of rail track and jacking boogies as per the Dockwise
Offloading Procedure;
-
Provision of on-site supervision during offloading operation.
Project Photographs
|
|
|
Dock Express 10 arrives at the new extension of the Freeport Container Terminal. |
|
|
|
The second crane being offloaded with its landside sillbeam supported by the jack boogies. |
|
|
|
Rotating the waterside trucks after moving the ship forward. |
|
|
|
Third and last crane getting ready for offloading, following the same procedure. |
|
|
|