![[ The barge safely pulled out from under rig ]](../images/Development%20Driller%20I%20free%20from%20barge.jpg)
After ballasting down, the barge is pulled out from
under rig
Project Summary
In 2006, Argonautics Marine Engineering was involved in the
tow-out of the semi-submersible drilling rig GSF Development Driller I
from the Kiewit Offshore Services yard in Ingleside, TX, to deep water
offshore.
The GSF
Development Driller I was repaired at the yard after sustaining
damage in hurricane Katrina. With its 8 DP thrusters installed under the
rig pontoons, the total rig draft was the same as the water depth in the
channels to open water. To ensure sufficient bottom clearance and avoid
damaging these thrusters on the way out, the rig needed to be lifted
for the tow-out. A solution was found by inserting a large cargo barge
between the rig pontoons and partly deballasting it to provide the required
1.0 m
lift - a modern version of the old "ship camels" used in Amsterdam in
the 17-th century. Special support brackets with softwooden cribbing blocks were mounted
to the barge hull, in line with strong stiffeners inside the rig's cross braces. Time
domain analyses were performed to determine the limiting sea states for
towing the combined units offshore and for the barge removal.
On April 9,
the GSF Development Driller I supported by the Boabarge 16 was towed
out from the yard through the narrow La Quinta Channel and Corpus
Christi channel to the offshore deep water site for removal of the
barge. Early next morning, after confirmation that the good weather
window was holding, the barge was ballasted until the rig was floating
on its own and sufficient clearance
was obtained between the barge supports and the rig braces. The
barge was then pulled out from under the rig and deballasted for
demobilization.
Scope
of Work
The project scope
included:
-
Feasibility study comparing the various rig draft reduction options;
-
Verify suitability of selected cargo barge;
-
Design support
brackets, guide posts, and cribbing arrangements;
-
Provide all procedures, including ballast plans, weather limits,
risk analysis, etc.;
-
Provide on-site
assistance during
barge insertion and
removal
operations.
Time Domain Analysis Video
A short video showing the results of the MOSES time domain analysis
for the combined units in 6 ft bow quartering seas. Requires Windows Media Player.
Time domain analysis...
Project Paper
A paper on this
successful tow-out was presented at the 26th International Conference on
Offshore Mechanics and Arctic Engineering in San Diego, CA, June 10-15,
2007...
Project Photographs
|
|
|
Boabarge 16 ready to be moved under the rig. |
|
|
|
Rig braces supported by special brackets. |
|
|
|
Bow of barge protruding out from under rig. |
|
|
|
Rig with barge towed-out from the yard to deeper waters. |
|
|
|