![[ Fairlift arriving with bauxite unloader components ]](../images/Bauxite%20Unloader%20arrival.jpg)
Fairlift arrives with the partly dismantled bauxite
unloader
Project Summary
A 2,000
t/hr Bauxite Shipunloader was delivered to the Alunorte pier in Vila do
Conde, Brazil, in September 1996. This shipunloader, designed by
Italimpianti and built by Sade Vigesa, had been erected at the Verolme
yard in Angra dos Reis, Brazil. For the ocean transportation, the
heavy-lift ship Fairlift, owned and operated by Jumbo Navigation
N.V., was contracted. The bucket elevator type shipunloader, weighing
approximately 1,100 t, was disassembled and its three major parts
were lifted onto the heavy-lift ship using the Verolme gantry crane.
Each part was then secured for the voyage using Jumbo's standard slings
and turnbuckles. On August 19, the seafastening operation was completed
and the Fairlift departed.
Early
morning on August 27, the ship arrived at the offloading pier in Vila do
Conde. Immediately upon arrival, the lashings of the gantry were removed
and the gantry was lifted from the ship onto the quay rails, using the
Fairlift's aft crane. After preparation of the 8 m diameter ball
bearing, the 335 t upper part was lifted from the ship and positioned
onto the gantry. For this lift, both ship cranes with a combined lifting
capacity of 650 t were used.
The Fairlift than shifted towards
the end of the pier, after which the shipunloader boom was connected
with the bucket elevator, still stowed on the ship's deck. The concrete
counter weight blocks as well as the two tie rods were installed, using
a mobile crane. Upon completion of the counter weight installation, the
shipunloader was able to safely lift the bucket elevator free from the
heavy-lift ship.
Argonautics Marine Engineering was hired
by Sade Vigesa to assist with the transportation engineering and on-site
assistance of the loading and offloading operations.
Scope
of Work
The project scope
included:
-
Confirm
feasibility of transportation and re-assembly of the bauxite
shipunloader;
-
Review of all
loading/transportation/offloading procedures;
-
Independent
stability and ship motion analyses;
-
Structural
analysis of the shipunloader parts subjected to lifting forces;
-
Structural
analysis of the shipunloader parts subjected to dynamic loading
during transport;
-
Designs for
internal strengthening and seafastening of loose parts;
-
On-site assistance
during loading, internal seafastening and offloading/assembly
operations.
Project Photographs
|
|
|
The gantry was lifted off the ship and set onto its shore rails by the ship's aft crane. |
|
|
|
The upper section was lifted by both ship cranes in tandem and set onto the gantry ball bearing. |
|
|
|
Using a mobile shore crane, the concrete counter weights were installed. |
|
|
|
The bucket elevator was connected to the lift arm and lifted free of its transportation support frame. |
|
|
|