![[ The new generators arrive on the cargo barge ]](../images/Arkansas%20Turbines.jpg)
The 2 new generators arrive on the cargo barge Paul
Bunyan
Project Summary
To replace 2 old
steam generators at the Arkansas Nuclear One power plant, 2 new
generators, each weighing approx. 550 t, were delivered on the cargo
barge Paul Bunyan in June of 2000. At a special prepared
unloading slip off Lake Dardanelle, the barge was carefully ballasted
down and grounded. Hydraulic multi-wheel trailers were rolled onboard
and each generator was rolled off and moved to a temporary storage area
for installation later.
Detailed procedures
were provided to pre-ballast the barge, ground the barge and maintain
adequate and safe bottom reaction throughout the two roll-off
operations.
Scope
of Work
The project scope
included:
Acknowledgement
Photograph courtesy
of Rigging International, Inc.
|