[ The new generators arrive on the cargo barge ]

The 2 new generators arrive on the cargo barge Paul Bunyan

Project Summary

To replace 2 old steam generators at the Arkansas Nuclear One power plant, 2 new generators, each weighing approx. 550 t, were delivered on the cargo barge Paul Bunyan in June of 2000. At a special prepared unloading slip off Lake Dardanelle, the barge was carefully ballasted down and grounded. Hydraulic multi-wheel trailers were rolled onboard and each generator was rolled off and moved to a temporary storage area for installation later.

Detailed procedures were provided to pre-ballast the barge, ground the barge and maintain adequate and safe bottom reaction throughout the two roll-off operations.    

Scope of Work

The project scope included:

  • Detailed ballast procedure for grounding the barge and maintaining bottom reaction;

  • Ballast procedure to re-float the barge after completion of the roll-off operations.

Acknowledgement

Photograph courtesy of Rigging International, Inc.

Home / Services / Projects / References / Publications / Search / Downloads / Contact Us / Industry Links / Client Login

Send mail to webmaster@argonautics.com with questions or comments about this web site.
Copyright © 1992 - 2010 ARGONAUTICS MARINE ENGINEERING, INC.
Last modified: 08/06/10