Arkansas Generators
 

Home
Up
Services
Projects
References
Publications
Search
Contact Us
Client Login

[ Engineered by Argonautiocs Marine Engineering Inc. ]


Providing
marine
 engineering
 services
 since 1992

[ The new generators arrive on the cargo barge ]

The 2 new generators arrive on the cargo barge Paul Bunyan

Project Summary

To replace 2 old steam generators at the Arkansas Nuclear One power plant, 2 new generators, each weighing approx. 550 t, were delivered on the cargo barge Paul Bunyan in June of 2000. At a special prepared unloading slip off Lake Dardanelle, the barge was carefully ballasted down and grounded. Hydraulic multi-wheel trailers were rolled onboard and each generator was rolled off and moved to a temporary storage area for installation later.

Detailed procedures were provided to pre-ballast the barge, ground the barge and maintain adequate and safe bottom reaction throughout the two roll-off operations.    

Scope of Work

The project scope included:

  • Detailed ballast procedure for grounding the barge and maintaining bottom reaction;

  • Ballast procedure to re-float the barge after completion of the roll-off operations.

Acknowledgement

Photograph courtesy of Rigging International, Inc.

Home ] Up ] Services ] Projects ] References ] Publications ] Search ] Contact Us ] Client Login ]

Send mail to webmaster@argonautics.com with questions or comments about this web site.
Copyright © 1996 - 2008 ARGONAUTICS MARINE ENGINEERING, INC.
Last modified: 03/19/08