
Stellaprima departs, loaded with an alumina shiploader
Project Summary
A 1,500
t/hr alumina shiploader was delivered to the Alunorte pier in Vila do
Conde, Brazil, in February 1996. This shiploader, designed and built by
Sade Vigesa, had been erected at the Verolme yard in Angra dos Reis,
Brazil. For the ocean transportation, the heavy-lift ship Stellaprima,
owned and operated by Jumbo Navigation NV, was contracted. The shiploader, weighing approximately 300 t, was lifted onto the
heavy-lift ship using the Verolme gantry crane and was then secured for
the voyage using Jumbo's standard slings and turnbuckles. Seafastening
took less than 24 hours and on February 6, the Stellaprima
departed Angra dos Reis with destination Vila do Conde. The voyage was
without incident, with maximum reported roll angles on the order of 4
degrees
Early
morning on February 13, the ship arrived at the offloading pier in Vila
do Conde. Immediately upon arrival, the lashings were removed and the
lifting beams were rigged and installed in place under the lower
platform of the shiploader. The following morning, the shiploader was
lifted from the ship onto its quay rails, using the Stellaprima's
own cranes, which have a combined safe working load of 650 t.
Argonautics Marine Engineering was hired by Sade Vigesa to assist with
the transportation engineering and on-site supervision of the loading
and offloading operations. As part of the scope, a Finite Element study
was done. The 3-dimensional structural model of the shiploader consisted
of over 600 beam elements. One of the reasons for making such a detailed
model was to accurately determine the weight and center of gravity of
the structure, since these were critical for the lifting operation.
Scope
of Work
The project scope
included:
-
Review
of all loading/transportation/offloading procedures;
-
Independent stability and ship motion analyses;
-
Structural analysis of the shiploader subjected to lifting forces;
-
Full
structural analysis of the shiploader subjected to dynamic loading
during transport;
-
Designs for internal strengthening and securings of loose parts;
-
On-site assistance during loading, internal seafastening and
offloading operations.
Project
Article
This successful transportation of the
Alumina shiploader was featured in the April 1996 issue of the "Maritime
Reporter and Engineering News"...
Project Photographs
|
|
|
At the construction yard, the shiploader was lifted onto the ship using the large 600 t capacity gantry crane. |
|
|
|
The shiploader was seafastened by the crew, using a large number of slings and turnbuckles. |
|
|
|
A Finite Element structural analysis was perfomed to confirm the feasibility of the lift by the ship cranes. |
|
|
|
The shiploader lifted from the ship onto the shore rails, using the two ship cranes and heavy lifting beams. |
|
|
|