![[ Bridge ready to be rolled on ]](../images/Fourth%20Street%20Bridge%20-%20Rolling%20on.JPG)
San Francisco 4-Th Street bridge ready to be rolled on at
high tide
Project
Summary
The 90-year-old bascule 4-th Street bridge (also known as the Peter R.
Maloney bridge), designed by Joseph Strauss of Golden Gate Bridge fame,
underwent an extensive seismic retrofit and massive structural overhaul.
After completion, it needed to be installed again
over the Mission Channel in San Francisco. For the
removal in 2003, see our Removal 4-th Street
Bridge project page.
Early morning on May 12, 2005, using two sets of
Goldhofer trailers, the bridge was slowly rolled onto the Dutra barge 217
at high tide, while ballasting the barge to control the heel. Once the
bridge was completely on board, the barge was maneuvered into position,
with the bridge pins over the bearing saddles. The barge was then ballasted
down to a minimum freeboard of 12 inches. The tide did the rest. Once
the barge was close to its support points, the trailers were lowered to
make first contact. The load was fully transferred by additional ballasting and
once free, the
barge with trailers and support beams was pulled out from under the
bridge at low tide.
Scope
of Work
The project scope
included:
- Verify feasibility of the
proposed cargo barge;
- Check of barge stability throughout the
various phases of rolling on and set down;
- Design of detailed ballast
procedures for rolling the bridge onto the barge;
- Provision of on-site assistance
during the bridge loading/installation operation.
Project Photographs
|
|
|
Trailers with bridge arrived at the ramp plates, ready to start rolling on. |
|
|
|
Barge with bridge moved into position for lowering bridge. |
|
|
|
Bridge pins lowered onto bearing saddles by ballasting and falling tide. |
|
|
|
At low tide, after completion of load transfer, the barge was pulled out. |
|
|
|